ATAN Schedule by Round
Meetings dates are subject to change.
Action/Activity |
Round 1 |
Round 2 |
Round 3 |
Round 4 |
Round 5 |
Issue Call for Projects |
06/05/17 |
08/31/17 |
02/12/18 |
09/06/18 |
02/11/19 |
Application Workshop |
6/20/17 |
9/19/17 |
2/15/18 |
09/20/18 |
02/28/19 |
Due Date for Requests |
07/07/17 |
11/02/17 |
04/05/18 |
11/01/18 |
04/11/19 |
MAG Compile Requests |
07/07 - 7/18/17 |
11/06 – 11/18/17 |
04/05 - 04/19/18 |
11/01 – 11/15/18 |
04/11 – 04/18/19 |
Evaluate at Transit Committee |
07/18/17 |
11/28/17 |
04/19/18 |
11/15/18 |
04/18/19 |
Recommend at Transportation Review Committee |
07/27/17 |
12/07/17 |
04/26/18 |
12/06/18 |
04/25/19 |
Recommend at Management Committee |
08/09/17 |
01/10/18 |
05/09/18 |
01/09/19* |
05/08/19 |
Regional Council Approval |
08/30/17 |
01/31/18 |
05/23/18 |
01/30/19* |
05/22/19 |
Issue Award Letters |
08/31 - 09/07/17 |
01/25 – 01/31/18 |
05/24 - 05/31/18 |
01/31 – 02/08/19 |
05/22 – 05/29/19 |
Agency amends/develops and approves IGA with VM |
08/30 - 12/1/17 |
11/29/17 – 04/30/18 |
05/24 - 08/23/18 |
01/31 – 04/30/19 |
05/29 – 08/29/19 |
One year clock begins at 3 months after RC action |
12/01/17 |
04/30/18 |
08/23/18 |
04/30/19 |
08/29/19 |
Agency builds improvements and submits monthly/quarterly reimbursement requests |
12/01/17 - 12/01/18 |
04/30/18 - 04/30/19 |
08/23/18 - 08/23/19 |
04/30/19 – 04/30/20 |
08/29/19 – 08/28/20 |
Cut off for request for reimbursements |
12/01/18 |
04/30/19 |
08/23/19 |
04/30/20 |
08/28/20 |
Agency takes pictures of work completed and submits to MAG |
01/01/19 |
05/10/19 |
09/06/19 |
05/08/20 |
09/18/20 |
Report generated with available funding from this round |
01/31/19 |
05/31/19 |
09/30/19 |
05/29/20 |
09/30/20 |
Round 1 July 7, 2017 Funding Requests
Round 2 November 2, 2017 Funding Requests
Round 3 April 5, 2018 Funding Requests
Round 4 November 1, 2018 Funding Requests
Round 5 - April 11, 2019 Funding Requests