2019 Specifications and Details Cases Under Consideration

Each year the MAG Standard Specifications and Details Committee reviews changes to the Uniform Standard Specifications and Details for Public Works Construction document. These changes are first reviewed in separate cases. This project page is designed to be a resource for committee members to access the most current versions of cases under consideration throughout the year. 

(Page last updated 12/30/19)

A summary of 2019 Cases with links to PDF working documents is shown in the table below:

Case 
Number
Description
of Case
Sponsor/
Agency
Date
Submitted

Last
Revision

Voting
Status
Comments/
Updates
Case 18-05 Revisions to Detail 145 Safety Rail (anchorage.)  Update wall thickness on Headwall details 501-1, 501-2, 501-4, 501-5 and 502-1. Karl Rockwell, MCDOT 02/07/18 02/07/19

Approved
03/06/19

 
Case 18-10 New Detail 238-4: Single Sidewalk Ramp, Mid-Block Residential with 4” Roll Curb. Revise Detail 221. Karl Rockwell, MCDOT 06/06/18 06/06/19 Approved
07/03/19
Chandler
Comments
Case 18-14:

Polymer concrete manhole construction. New polymer concrete manhole details 419-1, 419-2 and 419-3. New specifications Section 744.

Craig Sharp,
Buckeye

07/11/18 07/31/19 Approved
08/07/19
Phoenix
Comments
Case 19-01:

Miscellaneous Corrections:
A.Update Section 719 to show two-year approvals for mix designs in both locations.
B. Printing error in What’s New pages.
C. Update references and links in Index
D. Update references to testing to go to Section 611
E. Correct references to 404-1 and 404-3.
F. Correct typographic errors including missing colons in headings.
G. Misc. corrections from Avondale (spelling and typos).
H. Correct references to ADOT details in Section 206.5.1
I.  Correct misspelling of “MANUFACTURES” to “MANUFACTURERS” in manhole frame and cover details 423-1, 423-2, 424-1, 424-2.

Greg Groneberg,
Karl Rockwell,
Warren White,
Jim Badowich
02/06/19 08/23/19 Approved
09/04/2019
 
Case 19-02: Update Details 200-1 and 200-2 to show joint cut and patch detail and/or notes. Warren White,
Chandler
01/09/19 05/28/19 Approved
09/04/2019
 
Case 19-03: Revisions to Section 713: Emulsified Asphalt Materials Jose Rodriguez,
Phoenix
04/03/19 05/29/19 Approved
07/03/19
 
Case 19-04: Revisions to Section 360: Telecommunications Installation Warren White,
Chandler
04/03/19 05/23/19 Carry Forward MCDOT
Comments
Case 19-05: Revisions to Detail 262: Wing Type Alley Entrance Karl Rockwell, MCDOT 05/01/19 06/06/19 Approved
07/03/19
 
Case 19-06: Revisions to Section 321.14.4: Add information about process and materials used to patch core holes Greg Groneberg, Asphalt WG 07/03/19 07/03/19 Approved
09/04/2019
 
Case 19-07: Revisions to Section 331 Micro-surfacing Treatments and Section 714 Micro-surfacing Materials Jose Rodriguez,
Phoenix
07/03/19 08/27/19 Approved
09/04/2019
 
Case 19-08: Revisions to Section 332 Slurry Seal Treatments and Section 715 Slurry Seal Materials Jose Rodriguez,
Phoenix
07/03/19 08/27/19 Approved
09/04/2019
 
Case 19-09: New Section 626 Corrosion Coating of Sanitary Sewer Manholes Jim Badowich, Avondale, Water/Sewer WG 07/03/19 08/27/19 Carry Forward  
Case 19-10: New Section 627 Painting Sanitary Sewer Manholes with Insecticide Jim Badowich, Avondale, Water/Sewer WG 07/03/19 08/27/19 Approved
09/04/2019
 
Case 19-11: Revisions to Section 611: Add Sanitary Sewer Manhole Vacuum Testing Jim Badowich, Avondale, Water/Sewer WG 07/03/19 08/27/19 Carry Forward  
Case 19-12: Revisions to Detail 550 Spillway Inlet and Outlet: Clarify geometry/dimensions Karl Rockwell, MCDOT 07/03/19 07/03/19 Carry Forward